scott.hannaford scott.hannaford is offline How can I ignore historic over-allocation Windows 7 32bit How can I ignore historic over-allocation Office 2010 32bit
Novice
How can I ignore historic over-allocation
 
Join Date: Oct 2013
Posts: 2
scott.hannaford is on a distinguished road
Default How can I ignore historic over-allocation

Hi

is there any way that when you click onto the "next overallocation" button it can only do from today forwards?

For example, I have a resource who was on annual leave 1st -14th August but had a task assigned to her 1st July 2013 - 1st October 2014. As I have her as unavailable 1st -14th August, she was over allocated for those two weeks.



This means that when i click onto "next overallocation" it jumps me to the historic overallocation and not the next overallocatoin going forward from today. I know i can split the task and put the gap in for when she is on leave, but is there just a simple way for ignoring all previous over-allocations?
Reply With Quote
  #2  
Old 10-23-2013, 06:22 AM
JulieS JulieS is offline How can I ignore historic over-allocation Windows 7 64bit How can I ignore historic over-allocation Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

A couple of choices:
Assuming you are using Project 2010, in the Gantt chart view, right click on the overallocation indicator, and select "ignore problems for this task".

A better answer (in my opinion) is to make sure you have tracked the past tasks. Assuming the resource did not work during her vacation, enter zero for the actual hours during her vacation (Task Usage view) and the overallocation message should disappear for that task. (Assuming she is not still overallocated in the future).
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
How can I ignore historic over-allocation How to ignore the in between cells? babapusy Excel 1 01-21-2013 03:05 AM
How can I ignore historic over-allocation Resource Allocation OTPM Project 7 10-05-2012 03:40 AM
Ignore Resource Work Times JR_12 Project 2 12-05-2011 06:35 PM
How can I ignore historic over-allocation Ignore Duplicate Emails IanKM Outlook 1 10-20-2011 11:02 AM
How can I ignore historic over-allocation Ignore a section in grammar checker stlsailor Word 1 07-28-2009 12:45 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:18 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft