Hi
is there any way that when you click onto the "next overallocation" button it can only do from today forwards? For example, I have a resource who was on annual leave 1st -14th August but had a task assigned to her 1st July 2013 - 1st October 2014. As I have her as unavailable 1st -14th August, she was over allocated for those two weeks. This means that when i click onto "next overallocation" it jumps me to the historic overallocation and not the next overallocatoin going forward from today. I know i can split the task and put the gap in for when she is on leave, but is there just a simple way for ignoring all previous over-allocations? |
|
![]() |
||||