Over-allocated resource - resource holiday
 
Join Date: Oct 2013
Posts: 2
scott.hannaford is on a distinguished road
Default Over-allocated resource - resource holiday

I have set up, on resource sheet, all of the resources to be used in my project plan. I have used the resource availability field to enter when users are on holiday (set units at 0% for the duration they are off, and back to 100% for their return).

Now, for example, a resource has been indicated as Project Manager resource for 1st November 2013 to 1st February 2014, but as they are on leave 1st - 7th December, they come up as being over-allocated as they are allocated as PM during the week they are off.



Is there any way I can get Project to ignore the period when their availability is set to 0%, or is there somewhere else I need to add their holidays in?
Reply With Quote
  #2  
Old 10-21-2013, 05:32 AM
JulieS JulieS is offline Over-allocated resource - resource holiday Windows 7 64bit Over-allocated resource - resource holiday Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The holidays should be recorded as non-working time exceptions in the Resource's calendar. Changing a resources availability by manipulation of the max units does not automatically shift the task - it just flags the resource as overallocated.

Change the resource's calendars and Project will automatically shift the task so it is worked on only during working time.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
resource issue safaa Project 1 11-20-2012 05:41 AM
Over-allocated resource - resource holiday Resource Allocation OTPM Project 7 10-05-2012 03:40 AM
Over-allocated resource - resource holiday Allocation of resource Tray Project 3 06-01-2012 03:09 AM
Resource Status BrownHornet Outlook 0 04-12-2012 10:47 PM
Over-allocated resource - resource holiday new name for outlook resource Rayat Outlook 1 07-05-2011 04:12 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:05 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft