#1
|
|||
|
|||
![]() I have set up, on resource sheet, all of the resources to be used in my project plan. I have used the resource availability field to enter when users are on holiday (set units at 0% for the duration they are off, and back to 100% for their return). Now, for example, a resource has been indicated as Project Manager resource for 1st November 2013 to 1st February 2014, but as they are on leave 1st - 7th December, they come up as being over-allocated as they are allocated as PM during the week they are off. Is there any way I can get Project to ignore the period when their availability is set to 0%, or is there somewhere else I need to add their holidays in? |
#2
|
|||
|
|||
![]()
The holidays should be recorded as non-working time exceptions in the Resource's calendar. Changing a resources availability by manipulation of the max units does not automatically shift the task - it just flags the resource as overallocated.
Change the resource's calendars and Project will automatically shift the task so it is worked on only during working time. |
![]() |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
resource issue | safaa | Project | 1 | 11-20-2012 05:41 AM |
![]() |
OTPM | Project | 7 | 10-05-2012 03:40 AM |
![]() |
Tray | Project | 3 | 06-01-2012 03:09 AM |
Resource Status | BrownHornet | Outlook | 0 | 04-12-2012 10:47 PM |
![]() |
Rayat | Outlook | 1 | 07-05-2011 04:12 AM |