sofia sofia is offline How does "fixed work" work? Windows 7 64bit How does "fixed work" work? Office 2010 64bit
Novice
How does "fixed work" work?
 
Join Date: Sep 2013
Posts: 3
sofia is on a distinguished road
Default How does "fixed work" work?

Hello everybody,

I am working on a project and I've set the task type as "Fixed Work". I have scheduled my resources to work 8 hours per day. My problem is what hours to insert in Work Field > Task Form.
For example, if a task has a duration of 3 days and 1 resource assigned with 200% units, what do I insert in Work field? 24 hours or 48 hours?

Every suggestion and correction about the way I verge on the issue is more than welcome!

Thank you in advance,
Sofia.
Reply With Quote
  #2  
Old 10-20-2013, 07:28 AM
JulieS JulieS is offline How does "fixed work" work? Windows 7 64bit How does "fixed work" work? Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hello Sofia,

When you assign resources to tasks, Project will calculate one of the 3 variables:
  • You assign a resource to a task where Project only "knows" duration - Project will use the resource's maximum units and calculate the work based upon the equation: Duration * Units = Work.
  • You assign a resource to a task and you tell Project how much work it is - Project will again use the resource's maximum units and recalculate the task duration based upon the equation: Work/Units = Duration.
  • You assign a resource to a task and you have told Project both how much work and the task duration - Project will calculate the Assignment Units based upon the equation: Work/Duration = Units.
Task types (fixed work, fixed units, fixed duration) are used to control the calculation Project performs when you change one of the variables in the mathematics relationship between Work, Duration, and Assignment units in Microsoft Project. If after Project knows all three variables (Work, Duration, and Assignment units), you start changing one of the variables, that is where Task Type comes in. When you set a Task Type, you are telling Project which variable (work, duration, or units) you do not wish to change if you change one of the other variables.

For example:

If a task is Fixed Work:
  • If you change Duration - Project recalculates Assignment Units.
  • If you change Assignment Units - Project recalculates Duration.
  • If you change Work - Project recalculates Assignment Units.
If a task is Fixed Duration:
  • You change Work - Project recalculates Assignment Units.
  • You change Units - Project recalculates Work.
  • You change Duration - Project recalculates Work.

If a task is Fixed Units:
  • You change Work - Project recalculates Duration.
  • You change Duration - Project recalculates Work.
  • You change Assignment Units - Project recalculates Duration.
So, to your question:


If you have a task duration of 3 days - and assign a resource at 200%, Project will calculate 48 hours of work. However - assigning a resource at 200% will usually cause the resource to be overallocated if the resource's max units are set to 100%.


If you know how much work a task is, you can specify the work and Project will calculate the duration. If a task is 24 hours of work and your resources are only available 8 hours per day, the task duration should be 3 days.


I hope this helps.
Reply With Quote
  #3  
Old 10-21-2013, 03:03 AM
sofia sofia is offline How does "fixed work" work? Windows 7 64bit How does "fixed work" work? Office 2010 64bit
Novice
How does "fixed work" work?
 
Join Date: Sep 2013
Posts: 3
sofia is on a distinguished road
Default

Hi JulieS,

thank you so much for your reply and advice.It was very helpful.

Regards, Sofia.
Reply With Quote
  #4  
Old 10-21-2013, 05:30 AM
JulieS JulieS is offline How does "fixed work" work? Windows 7 64bit How does "fixed work" work? Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome Sofia and thank you for the feedback.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How does "fixed work" work? Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Evgeny Project 3 01-03-2013 06:45 AM
How does "fixed work" work? How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
"Set as default shape" does not work pumpkin_feet Excel 1 02-01-2011 11:42 AM
Outlook- "Type A Contact To Find" Doesn't Work jill5545 Outlook 0 11-14-2010 08:45 PM
"Outlook could not create the work file." error. All settings look good, any ideas? Booshanky Outlook 0 08-31-2010 09:36 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:24 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft