any way to exclude activity from critial path
hello
i have a scaffolding activity, which effects the start date of construction activities, by a SS relationship. we are saying even after the construction activities finish, that scaffold will remain in place for a while. so, the scaffold end date is the latest. so the critical path automatically shows scaffolding. but i dont want that. i want to exclude the scaffolds form critical path calculation and critial path to calculate from the construction activities, even if they end earlier than scaffold end date. can i exclude the scaffolding activities from critical path calculation, but still keeping the link between it and the construction activities? |
#2
|
|||
|
|||
Consider breaking the scaffolding activities into two parts - put up the scaffolding and remove.
You can still link put up to the construction and remove as a successor to construction. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
SQL db query to exclude some entries | jillapass | Excel | 1 | 11-09-2012 04:53 AM |
tying to a critical activity | ketanco | Project | 1 | 08-04-2012 05:59 AM |
Exclude phrase from email | kiwiora | Outlook | 2 | 07-16-2012 03:03 PM |
changing one activity in a baseline | ketanco | Project | 5 | 02-11-2012 07:24 AM |
updating a delayed activity | ketanco | Project | 3 | 01-26-2012 01:47 PM |