Hello everybody,
I am working on a project and I've set the task type as "Fixed Work". I have scheduled my resources to work 8 hours per day. My problem is what hours to insert in Work Field > Task Form. For example, if a task has a duration of 3 days and 1 resource assigned with 200% units, what do I insert in Work field? 24 hours or 48 hours? Every suggestion and correction about the way I verge on the issue is more than welcome! Thank you in advance, Sofia. |
|
![]() |
||||