AmezNez AmezNez is offline How to have multiple blocks of duration for one task Windows 7 32bit How to have multiple blocks of duration for one task Office 2010 32bit
Novice
How to have multiple blocks of duration for one task
 
Join Date: Oct 2013
Posts: 4
AmezNez is on a distinguished road
Default How to have multiple blocks of duration for one task

Hi everyone



I'm currently building a project plan and trying to have some tasks at the very bottom that would show people's availability i.e. when they are on vacation.

The problem is I can't see how to have more than one block of duration. So for example if they were on holiday for a week in December then 2 weeks in March. I would want the task duration to block out these periods so you could easily see it on the Gantt chart.

Anyone know how I can do this?

I imagine it must be possible as in project you could easily have tasks that stop and start throughout the duration i.e. gaps for other tasks to complete etc

Thanks a lot!
Reply With Quote
  #2  
Old 10-10-2013, 05:32 AM
JulieS JulieS is offline How to have multiple blocks of duration for one task Windows 7 64bit How to have multiple blocks of duration for one task Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You can manually edit the work information in the Task Usage or Resource Usage view.
Create the "vacation" task for each user, switch to the Task Usage or Resource Usage view and enter the days off as work in the View. The task will show splits in the Gantt view.
Reply With Quote
  #3  
Old 10-10-2013, 05:53 AM
AmezNez AmezNez is offline How to have multiple blocks of duration for one task Windows 7 32bit How to have multiple blocks of duration for one task Office 2010 32bit
Novice
How to have multiple blocks of duration for one task
 
Join Date: Oct 2013
Posts: 4
AmezNez is on a distinguished road
Default

Thanks that's really useful!
Reply With Quote
  #4  
Old 10-10-2013, 05:55 AM
JulieS JulieS is offline How to have multiple blocks of duration for one task Windows 7 64bit How to have multiple blocks of duration for one task Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome.
Reply With Quote
Reply

Tags
duration, multiple, tasks



Similar Threads
Thread Thread Starter Forum Replies Last Post
How to have multiple blocks of duration for one task Linking task duration to another task branchi Project 1 08-15-2013 06:03 AM
How to have multiple blocks of duration for one task Question related to actual duration of task Mac235 Project 1 08-14-2013 06:54 AM
How to have multiple blocks of duration for one task overtime work effecting task duration user0044 Project 11 03-06-2012 07:20 AM
Task duration between 2 fixed milestones cettolox Project 3 01-24-2012 06:33 AM
Multiple task lists and multiple calendars kballing Outlook 0 01-18-2011 10:23 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:18 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft