Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 10-04-2013, 12:43 PM
dburnt dburnt is offline Replicating tasks in a single project Windows 8 Replicating tasks in a single project Office 2013
Novice
Replicating tasks in a single project
 
Join Date: Oct 2013
Location: Ontario
Posts: 3
dburnt is on a distinguished road
Default Replicating tasks in a single project

I have a project with a series of phases. Each phase has some identical tasks and some unique ones. I would like to copy the tasks into the phases rather than rebuilding them.

When I try to copy them, the links do not properly update.

For example, I have 80 rows of data, with dependencies, etc. I copy rows 10 to 50...they become rows 150 to 190. However, the dependencies still show to row 15 for example, rather than to row 165.



Is there a way to copy tasks and have the dependencies update to reflect the new rows (this works fine in Excel for example, the cell references update).

I should note, this is a work project using MS Project 2003 (updating to 2010 shortly)
Reply With Quote
  #2  
Old 10-04-2013, 03:13 PM
JulieS JulieS is offline Replicating tasks in a single project Windows 7 64bit Replicating tasks in a single project Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Are you selecting the task by the row number and then copying? Have you tried collapsing the summary task, copying the summary and pasting? What service pack do you have applied to Project 2003? I believe it is up to SP-3
Reply With Quote
  #3  
Old 10-04-2013, 03:15 PM
dburnt dburnt is offline Replicating tasks in a single project Windows 8 Replicating tasks in a single project Office 2013
Novice
Replicating tasks in a single project
 
Join Date: Oct 2013
Location: Ontario
Posts: 3
dburnt is on a distinguished road
Default

I have tried copying by row, by cell, only some cells, etc. Each time is the same result.

I will update tomorrow with the update version. Thanks.
Reply With Quote
  #4  
Old 10-07-2013, 05:57 AM
dburnt dburnt is offline Replicating tasks in a single project Windows 8 Replicating tasks in a single project Office 2013
Novice
Replicating tasks in a single project
 
Join Date: Oct 2013
Location: Ontario
Posts: 3
dburnt is on a distinguished road
Default

it is SP3

However, I tried again with the structure collapsed, and the dependencies shifted properly.

thanks!
Reply With Quote
  #5  
Old 10-07-2013, 07:41 AM
JulieS JulieS is offline Replicating tasks in a single project Windows 7 64bit Replicating tasks in a single project Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Great. The trick is to collapse the summary tasks and then copy the entire task - it should keep all of the relationships within the summary task correctly. Glad all is sorted.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project tasks moving automatically tcalderini Project 3 09-06-2013 12:25 PM
Finding Earned Values for Different Baselines in a single project pratik6312 Project 1 08-22-2013 11:18 AM
Replicating tasks in a single project How to help - Project 2007 - Scheduling tasks during specific windows of opportunity apexian Project 1 07-12-2013 05:16 AM
Calender icons replicating AmyBrink Outlook 0 04-16-2013 01:04 PM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:38 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft