#1
|
|||
|
|||
Show multiple (near critical) paths
Hi guys,
I'm using MS Project 2010. I know that in order to display multiple critical paths I should go to the File tab, click advanced options and check the "calculate multiple critical paths" box. But with this option, the critical paths are displayed all together in one gantt chart. Is there any way i can see each near critical path separately? Thanks in advance!! |
#2
|
|||
|
|||
Hi Sofia,
I'm sorry I don't understand what you mean by "Is there any way i can see each near critical path separately". There is no such thing as "near critical" - task are either critical (Total Slack <=0) or not critical. Displaying multiple critical paths just traces each network path from beginning to end and calculates the tasks on that path which directly affect the end date of that path. You can insert the Total Slack field and use that for filtering and can combine it with a date range filter but I'm not sure this will get you what you need - as I'm not sure what you need. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
tying to a critical activity | ketanco | Project | 1 | 08-04-2012 05:59 AM |
How to show critical task bars in different color? | ketanco | Project | 1 | 05-17-2012 05:17 AM |
Two motion paths | iskenderbaris | PowerPoint | 0 | 04-12-2012 03:13 AM |
calculate multiple critical paths | ketanco | Project | 3 | 12-26-2011 09:29 AM |
motion paths | Cath5000 | PowerPoint | 0 | 07-29-2011 10:59 AM |