Another option is to add the task set it's duration to 1 day (fixed) with the resources assigned at 50%. Set a deadline on the task to ensure you get notified if it passes the deadline date. Keep an eye on the task during your status updates as human nature being what it is, they will delay working on the task until the deadline.
|
|
|