Passed due task end date
Is there a way to flag a task in project that has passed its end date but is not yet complete? I can change background color of the task name to identify it that was but am wondering is there is a way for the tool to do something automatically.
|
#2
|
|||
|
|||
I'm guessing you mean past its baseline finish? You could certainly apply a highlight filter looking for tasks with finish variance (assuming you have saved a baseline) that have % complete < 100%.
Another option is to use the Status Indicators. While they won't change background color, they will flag tasks that are late. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Task not rolling up after single task was baselined | Hwlr | Project | 1 | 06-05-2013 03:43 PM |
Task with Start date but no Due date? | bplat | Outlook | 0 | 01-12-2012 08:10 AM |
Help with Err in Outlook 2003> Certificate's CN name does mot match the passed value? | edmund36 | Outlook | 2 | 10-17-2011 06:15 AM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
Is it possible to show the Task due date in the calendar? | Lin | Outlook | 1 | 07-26-2010 05:34 AM |