#1
|
|||
|
|||
![]()
Hi all,
I am creating a plan for a client where I have some tasks they need to do. A task may only actually take them 0.5 day, but I don't mind when they do it as long as its done by a certain date. So I want to show on the plan for their guidance, for example start date- 01/10/13 (can start the task on or after this date) end date = 14/10/13 (task must be completed by this date) man days = 0.5 day (i.e. how long the task will actually take) Is this possible in MS Project Professional 2010 thanks |
|
![]() |
||||