Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 09-18-2013, 07:02 AM
loobs40 loobs40 is offline Start / End Dates in conjunction with man days Windows 7 32bit Start / End Dates in conjunction with man days Office 2010 32bit
Novice
Start / End Dates in conjunction with man days
 
Join Date: Sep 2013
Posts: 3
loobs40 is on a distinguished road
Default Start / End Dates in conjunction with man days

Hi all,



I am creating a plan for a client where I have some tasks they need to do.

A task may only actually take them 0.5 day, but I don't mind when they do it as long as its done by a certain date.

So I want to show on the plan for their guidance, for example

start date- 01/10/13 (can start the task on or after this date)
end date = 14/10/13 (task must be completed by this date)
man days = 0.5 day (i.e. how long the task will actually take)

Is this possible in MS Project Professional 2010

thanks
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
start and finish dates exceeding duration joday48 Project 0 06-27-2012 04:55 AM
Start / End Dates in conjunction with man days baseline duration, start and finsih dates ketanco Project 1 04-09-2012 09:47 AM
Start / End Dates in conjunction with man days Task Start and End Dates OTPM Project 2 12-04-2011 09:14 AM
start-stop month dates in calendar madison320 Project 0 06-24-2011 08:15 AM
Start / End Dates in conjunction with man days Setting Drop Dead Start Dates greenboard Project 2 06-14-2010 08:12 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:25 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft