#1
|
|||
|
|||
Project tasks moving automatically
Has anyone experienced the automatic moving of tasks within a plan. I have created a plan and saved it. I then close it or go to a different view. When I return, the order of some tasks has automatically changed. For example, when I saved the plan tasks 10 - 20 were all in numerical order. After going back to the Gantt view, my order can be something like this:
10 11 14 19 12 15 20 16 17 18 13 Any thoughts? Thanks |
#2
|
|||
|
|||
It looks like your view may have a sort order other than by ID. Try Project > Sort > Sort By and sort by ID.
|
#3
|
|||
|
|||
That seems to have worked. Thanks
|
#4
|
|||
|
|||
You're welcome and thanks for the feedback.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
moving tasks - retaining dependencies | Andy Francis | Project | 5 | 07-25-2013 10:24 AM |
How to help - Project 2007 - Scheduling tasks during specific windows of opportunity | apexian | Project | 1 | 07-12-2013 05:16 AM |
How to get project to automatically pull in task dates? | Moe Szylak | Project | 2 | 04-26-2012 12:37 PM |
Can I automatically save mpp files on a Project Server to 'shard docs' or elsewhere? | dksfwmcc | Project | 3 | 03-19-2012 09:09 AM |
I can't figure out how to get Project 2010 to automatically rebalance my schedule | jackofnothing | Project | 0 | 10-23-2011 04:04 PM |