Linking task duration to another task
how do i link the task duration to the end of a specific task rather than a set time, e.g i want to make 'task A' run from a certain date of the project until 'task B' is complete but if 'task B' was to get delayed then 'task A' would continue to run?? |
#2
|
|||
|
|||
You can paste-link the finish of task B as the finish of A. See the following article regarding hammock tasks.
http://support.microsoft.com/kb/141733/EN-US |
Tags |
task duration |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Question related to actual duration of task | Mac235 | Project | 1 | 08-14-2013 06:54 AM |
overtime work effecting task duration | user0044 | Project | 11 | 03-06-2012 07:20 AM |
Task duration between 2 fixed milestones | cettolox | Project | 3 | 01-24-2012 06:33 AM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
Linking a SharePoint meeting to a Project task. | mnollar | Project | 0 | 12-13-2005 03:58 PM |