Question related to actual duration of task
What assumptions Project 2010 make when you enter an actual duration value that is less than the remaining duration? Can anyone help me for this question? Thanks Mac |
#2
|
|||
|
|||
If you enter an actual duration that is less than the baseline duration, Project will assume the task is incomplete and has remaining duration. if the Task is complete with the lower duration value, set the Remaining Duration (Rem. Dur. field in the Tracking table) to zero.l
If you enter an actual duration that is greater than or equal to the baseline duration, Project will assume the task is complete. You may adjust Remaining Duration as needed. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
overtime work effecting task duration | user0044 | Project | 11 | 03-06-2012 07:20 AM |
updating status date and actual duration | ketanco | Project | 5 | 01-27-2012 07:32 AM |
Task duration between 2 fixed milestones | cettolox | Project | 3 | 01-24-2012 06:33 AM |
duration vs actual start and finish dates | ketanco | Project | 1 | 12-14-2011 09:06 AM |
Duration help (Quick question) | davy631 | Project | 3 | 03-07-2011 12:55 PM |