HELP!! We have formal scheduled meetings and change windows for tasks.
Example: Change control meetings always occur on Thursdays. I have mixed duration deliverables to be completed before going to "approval to proceed" meeting. I create critical-path milestones for the meeting. If i get everything done on Friday, i still need to wait until following thursday before any additional work can continue. If i finish on Wednesday, however, the next day i can go to the meeting. I have several bureaucratic approval "gates" to jump through, each with unique schedules. Is there a way, other than creating a bunch of special calendars and assigning tasks to those calendars to build the window/wait times into an individual task? Thanks for your help! |
#2
|
|||
|
|||
![]()
Making the custom calendars with "buffer" tasks is the most efficient manner. The other option is to constrain the tasks but require manual intervention.
|
![]() |
Tags |
calendar, meetings |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Sync Outlook 2010 contacts, calendar & tasks with Outlook.com & Windows Mobile 8 | TimTDP | Outlook | 0 | 01-04-2013 11:30 PM |
Scheduling conflicts in MS Project | Antares | Project | 1 | 01-24-2012 06:36 AM |
Export Excel tasks into Outlook Tasks (2007 Version on both) | crazedmom | Excel | 0 | 12-29-2011 07:55 AM |
Outlook completed tasks synced with Windows Mobile 6.5 | ghumdinger | Outlook | 0 | 07-03-2011 07:22 AM |
Scheduling of Tasks | asmith1977 | Project | 0 | 01-27-2011 11:13 AM |