Old 07-11-2013, 03:21 PM
dbsoccer dbsoccer is offline changing the standard display format Windows XP changing the standard display format Office 2007
Novice
changing the standard display format
 
Join Date: Apr 2012
Posts: 21
dbsoccer is on a distinguished road
Default changing the standard display format

I would like to show the gannt chart information on a single line. Let me better explain.



Consider a project with three phases and milestones between the phase. Phase 1: Investigation followed by milestone - POR Followed by Phase 2: Development followed by milestone - Release. Followed by Phase 3: Shipments followed by milestone - EOL.

I'd like to create these phases using the task duration, start date end date features in Project but report out these tasks and milestones on a single line (collapsing the 'task' details). With different colors for each phase and milestone.

Is this possible in Project?
Reply With Quote
  #2  
Old 07-12-2013, 05:19 AM
JulieS JulieS is offline changing the standard display format Windows 7 64bit changing the standard display format Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I would add the Project Summary task (Tools > Options, view tab in 2007). You can then select to rollup the task bars - or perhaps just the milestones - to the summary bar.

See:
http://office.microsoft.com/en-us/pr...045304026.aspx
Reply With Quote
  #3  
Old 07-12-2013, 10:58 AM
dbsoccer dbsoccer is offline changing the standard display format Windows XP changing the standard display format Office 2007
Novice
changing the standard display format
 
Join Date: Apr 2012
Posts: 21
dbsoccer is on a distinguished road
Default

Thanks Julie, I got that too albeit a bit more manual than I had hoped. I changed the colors of the sub task bars and I was hoping the the segments in teh summary task bar would have the same colors. It did not. I changed them manually.

But I have another question. I would like to display the Task Name for the summary bar to the left of the summary bar. I found websites that talk about a macro to use yet I don't have any macros preloaded in my version of Project. What do I need to do to get the task name associated with the summary task row to display? I can see how to get the task names to display next to their respective tasks lines but can't get the summary task name to display next to the summary task line.

Thanks.
Reply With Quote
  #4  
Old 07-12-2013, 01:46 PM
JulieS JulieS is offline changing the standard display format Windows 7 64bit changing the standard display format Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

In Format > Bar Styles you can add text to the left of the summary task bars.

You may also want to look into creating some task bar styles (using Flag fields) to create the different color roll up bars. It is more efficient than individual formatting.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
How to format cell in order to display *both* time and date SamyCode Excel 3 01-22-2013 03:30 PM
Changing Display Name in Inbox From Field amurray Outlook 3 04-18-2012 12:06 PM
Changing format of time data Sammael Excel 2 04-08-2012 12:13 PM
How to set standard format for all TDV Word 0 07-02-2011 09:41 PM
changing the standard display format Font colour and format changing? Lamya Word 5 05-16-2011 02:35 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:41 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft