Dear all,
I wonder it is possible to create a view, where I will bring both task and resource fields together?


If I assign resource to a task, I can then either go to task usage view, and then I will be able to insert columns with task fields or I can go to a resource usage and I will be able to show resource fields, but I need to have a view, where I would have possibility to show both types of fields. So in a way I would like to have an assignment table.
Specifically I would like to have a view, where for s specific assignment I would show Text1 field of a Task as well as Text1 field of a resource.
Is it possible?
Regards.
Evgeny
Reply With Quote
  #2  
Old 06-19-2013, 06:55 AM
JulieS JulieS is offline How to bring in one view task and resource fields? Windows 7 64bit How to bring in one view task and resource fields? Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Please see thread at:
http://answers.microsoft.com/en-us/o...d-f403b191ca06
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
outlook calander and task view muzzi Outlook 0 11-25-2012 05:36 AM
How to bring in one view task and resource fields? Two resource sheet for one task zapco76 Project 1 11-20-2012 05:43 AM
I am unsure I assigned a task out to a resource. jsteczak Project 3 10-05-2012 04:41 AM
How to bring in one view task and resource fields? Showing Text fields on GANTT and Resource NeoFax Project 4 06-07-2011 08:32 AM
Accessing Assignment Detail Data in Task Usage View CGM3 Project 0 10-05-2010 05:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:43 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft