#1
|
|||
|
|||
Task not rolling up after single task was baselined
I added a single task to my schedule. I set my baseline with the selected task. However the task does not role up to any of the summary tasks.
Under the set baseline options I have tried both Roll up baseline: options but no combination of the options resulted in the baseline % changing.. |
#2
|
|||
|
|||
Sorry, I don't understand.
What baseline% are you referring to? There are the following baselines fields: Baseline Start Baseline Finish Baseline Work Baseline Duration Baseline Costs The is no Baseline % field. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Assigning a single task to a team or group | djcozens | Project | 1 | 07-09-2012 05:44 AM |
How to set task to be done by 4 resources each one after another? | lukusm | Project | 1 | 01-16-2012 07:21 AM |
arrows remain between task bars, but predecessor info disappears from task info | Antares | Project | 1 | 12-14-2011 09:19 AM |
Task alert? | markg2 | Outlook | 1 | 03-30-2011 10:05 AM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |