#1
|
|||
|
|||
Tracking Gantt against Baseline 2
I have 3 baselines. Can I use Tracking Gantt view but select which of the baseline I want to view?
|
#2
|
|||
|
|||
Right click on the Gantt chart and select Bar Styles. Change the references in Baseline bars to Baseline3. Or duplicate the Baseline bar style( cut and paste twice) and then edit one of the bars.
You'll also need to change which baseline variance is calculated against. Go to Tools > Options, Calculation tab. click the Earned Value button and select Baseline3. I hope this helps. Julie |
#3
|
|||
|
|||
Thanks! That worked!
|
#4
|
|||
|
|||
You're welcome and thank you for the feedback.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Baseline query | joday48 | Project | 6 | 01-25-2013 09:50 AM |
changing one activity in a baseline | ketanco | Project | 5 | 02-11-2012 07:24 AM |
some work was complete at my baseline | ketanco | Project | 1 | 01-25-2012 02:45 PM |
Retrieve a baseline after it's been cleared | fridos | Project | 2 | 05-11-2011 10:08 AM |
Help with Interim Baseline Variance | poyns | Project | 1 | 05-27-2010 10:59 AM |