#1
|
|||
|
|||
Critical Task - Microsoft Project 2010
Can anyone explain me, when we see in network diagram of any project (which does not have any link between the tasks), the first task is being shown as "Critical Task" (with RED border)?
Thanks Mac |
#2
|
|||
|
|||
Because it is the only task with zero total slack. Critical path is calculated by project. Without further information - I can't give a more complete answer, sorry.
|
#3
|
|||
|
|||
Quote:
Please find attached here a sample project file. Project A has duration of 3 days, B has 2 days and C has 1 day. Please review the network diagram. Task A is on Critical path. If you change the duration of the tasks B & C as 3 days each, then they will also become "critical". Even if you change the start date of Task A to June 05, 2013 (keeping the same duration), it will show Task A as "critical". Will you please explain why this happnes? Thanks |
#4
|
|||
|
|||
None of your tasks are linked, therefore the task with the longest duration (initially Task a) is the task on the critical path - it is the task that is driving the latest date in the project. When you increase tasks b & C to 3 days duration they now all finish last and are all critical. Changing the start date of A to June 5 with 3 days duration still makes it finish last.
So, what are you expecting? |
#5
|
|||
|
|||
Thanks
Quote:
Thanks for your reply. The task with the longest duration is a "critical" task. |
#6
|
|||
|
|||
I don't know if this is a question or statement. In the project you had attached yes, the longest task was critical because it was the task driving the end date of the project. Critical is calculated mathematically - it is not subjective. You may have a task that you consider to be very important, but it may not be on the critical path.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
How to show critical task bars in different color? | ketanco | Project | 1 | 05-17-2012 05:17 AM |
Microsoft Project 2010 SYNC Problem | paul14louie | Project | 3 | 04-13-2012 11:36 AM |
Microsoft Project 2010 automation without VS | Fil | Project | 0 | 09-15-2011 10:17 AM |
MS Project 2010 Synch to task list | rinalgi1 | Project | 1 | 09-14-2011 12:37 AM |
Microsoft Project 2010 taking up to 10mins to open file from network share. | BITS | Project | 1 | 06-01-2011 09:37 AM |