Critical Task - Microsoft Project 2010
 
Join Date: May 2013
Posts: 5
Mac235 is on a distinguished road
Default Critical Task - Microsoft Project 2010

Can anyone explain me, when we see in network diagram of any project (which does not have any link between the tasks), the first task is being shown as "Critical Task" (with RED border)?

Thanks



Mac
Reply With Quote
  #2  
Old 05-30-2013, 05:27 AM
JulieS JulieS is offline Critical Task - Microsoft Project 2010 Windows 7 64bit Critical Task - Microsoft Project 2010 Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Because it is the only task with zero total slack. Critical path is calculated by project. Without further information - I can't give a more complete answer, sorry.
Reply With Quote
  #3  
Old 06-03-2013, 03:34 PM
Mac235 Mac235 is offline Critical Task - Microsoft Project 2010 Windows XP Critical Task - Microsoft Project 2010 Office 2007
Novice
Critical Task - Microsoft Project 2010
 
Join Date: May 2013
Posts: 5
Mac235 is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
Because it is the only task with zero total slack. Critical path is calculated by project. Without further information - I can't give a more complete answer, sorry.
Hi Julie,
Please find attached here a sample project file.
Project A has duration of 3 days, B has 2 days and C has 1 day.

Please review the network diagram. Task A is on Critical path. If you change the duration of the tasks B & C as 3 days each, then they will also become "critical".

Even if you change the start date of Task A to June 05, 2013 (keeping the same duration), it will show Task A as "critical".

Will you please explain why this happnes?

Thanks
Attached Files
File Type: pdf Project1.pdf (9.2 KB, 15 views)
Reply With Quote
  #4  
Old 06-03-2013, 04:27 PM
JulieS JulieS is offline Critical Task - Microsoft Project 2010 Windows 7 64bit Critical Task - Microsoft Project 2010 Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

None of your tasks are linked, therefore the task with the longest duration (initially Task a) is the task on the critical path - it is the task that is driving the latest date in the project. When you increase tasks b & C to 3 days duration they now all finish last and are all critical. Changing the start date of A to June 5 with 3 days duration still makes it finish last.

So, what are you expecting?
Reply With Quote
  #5  
Old 06-07-2013, 06:53 AM
Mac235 Mac235 is offline Critical Task - Microsoft Project 2010 Windows XP Critical Task - Microsoft Project 2010 Office 2007
Novice
Critical Task - Microsoft Project 2010
 
Join Date: May 2013
Posts: 5
Mac235 is on a distinguished road
Default Thanks

Quote:
Originally Posted by JulieS View Post
None of your tasks are linked, therefore the task with the longest duration (initially Task a) is the task on the critical path - it is the task that is driving the latest date in the project. When you increase tasks b & C to 3 days duration they now all finish last and are all critical. Changing the start date of A to June 5 with 3 days duration still makes it finish last.

So, what are you expecting?
Julie,

Thanks for your reply. The task with the longest duration is a "critical" task.
Reply With Quote
  #6  
Old 06-07-2013, 07:45 AM
JulieS JulieS is offline Critical Task - Microsoft Project 2010 Windows 7 64bit Critical Task - Microsoft Project 2010 Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I don't know if this is a question or statement. In the project you had attached yes, the longest task was critical because it was the task driving the end date of the project. Critical is calculated mathematically - it is not subjective. You may have a task that you consider to be very important, but it may not be on the critical path.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Critical Task - Microsoft Project 2010 How to show critical task bars in different color? ketanco Project 1 05-17-2012 05:17 AM
Critical Task - Microsoft Project 2010 Microsoft Project 2010 SYNC Problem paul14louie Project 3 04-13-2012 11:36 AM
Microsoft Project 2010 automation without VS Fil Project 0 09-15-2011 10:17 AM
MS Project 2010 Synch to task list rinalgi1 Project 1 09-14-2011 12:37 AM
Critical Task - Microsoft Project 2010 Microsoft Project 2010 taking up to 10mins to open file from network share. BITS Project 1 06-01-2011 09:37 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:28 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft