![]() Can anyone explain the difference between these two tasks with example? Thanks |
#2
|
|||
|
|||
![]()
Manually scheduled tasks do not respond to the project scheduling engine. You can enter start or finish dates for a manually scheduled task that are not during working time.
Autoscheduled tasks can only be scheduled during working time as defined in the task calendar. |
![]() |
|
![]() |
||||