#1
|
|||
|
|||
![]()
Is there a simple away that I can change the existing report 'Upcoming Tasks' to reflect a ten day period as opposed to one week? Alternatively, can I copy the report and then edit the parameters somehow?
|
#2
|
|||
|
|||
![]()
Hi,
There is no report called "Upcoming tasks". There is a "tasks starting soon report" that uses the Date Range filter. It sounds like this may be a custom report? It's difficult to suggest how to edit the report - without knowing how it is made - but generally, yes you can copy a report and edit the copy. To copy and existing report: Project tab, Reports Find the report and single click to select. Click the Edit button and give the report a new name. Assuming the report is running a filter, you should see the name of the filter appear on the definition page. You may need to modify the filter to include different date ranges. So - to help further - I'd need more information about the filter definition. Find the filter and look at the definition (View tab, filter drop down, more filters, edit) and post back with the details. Julie |
#3
|
|||
|
|||
![]()
Julie
Thanks for your prompt reply. I should have mentioned that I am using Project 2013, the reporting for which seems to have been designed differently. The Upcoming Tasks is a provided report. I cannot see how I can edit this. |
#4
|
|||
|
|||
![]()
Sorry - my installation of Project 2013 has no report named "Upcoming tasks" - so I'm still guessing it is a custom report.
Is it a table based report? If so, click in the table and on the field list on the right - there should still be an option for filters. To create a report - open the existing report, on the Report Tools - Design tab - select "Manage" to rename the report or Copy to create a copy of the report and edit. |
![]() |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Example Report | Hinchy | Word | 0 | 10-09-2012 07:00 AM |
Best way for tracking and report | Osama.Mujahed | Project | 3 | 02-05-2012 06:39 AM |
How to edit the "Format" and the "show level" of an EXISTING table of content? | Jamal NUMAN | Word | 2 | 08-14-2011 10:46 AM |
MarkAsFinal - 'Edit Anyway' edit popup issue | GovindRS | PowerPoint | 1 | 06-20-2011 06:43 AM |
Report creation. | Igtech | Excel | 1 | 04-02-2010 03:33 PM |