Edit of existing report
 
Join Date: Dec 2012
Posts: 4
abbertonian is on a distinguished road
Question Edit of existing report


Is there a simple away that I can change the existing report 'Upcoming Tasks' to reflect a ten day period as opposed to one week? Alternatively, can I copy the report and then edit the parameters somehow?
Reply With Quote
  #2  
Old 04-10-2013, 07:07 AM
JulieS JulieS is offline Edit of existing report Windows 7 64bit Edit of existing report Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi,

There is no report called "Upcoming tasks". There is a "tasks starting soon report" that uses the Date Range filter. It sounds like this may be a custom report? It's difficult to suggest how to edit the report - without knowing how it is made - but generally, yes you can copy a report and edit the copy.

To copy and existing report:
Project tab,
Reports
Find the report and single click to select.
Click the Edit button and give the report a new name.
Assuming the report is running a filter, you should see the name of the filter appear on the definition page.

You may need to modify the filter to include different date ranges.

So - to help further - I'd need more information about the filter definition.

Find the filter and look at the definition (View tab, filter drop down, more filters, edit) and post back with the details.

Julie
Reply With Quote
  #3  
Old 04-10-2013, 07:20 AM
abbertonian abbertonian is offline Edit of existing report Windows 7 32bit Edit of existing report Office 2013
Novice
Edit of existing report
 
Join Date: Dec 2012
Posts: 4
abbertonian is on a distinguished road
Default

Julie

Thanks for your prompt reply.

I should have mentioned that I am using Project 2013, the reporting for which seems to have been designed differently. The Upcoming Tasks is a provided report. I cannot see how I can edit this.
Reply With Quote
  #4  
Old 04-10-2013, 07:56 AM
JulieS JulieS is offline Edit of existing report Windows 7 64bit Edit of existing report Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Sorry - my installation of Project 2013 has no report named "Upcoming tasks" - so I'm still guessing it is a custom report.

Is it a table based report? If so, click in the table and on the field list on the right - there should still be an option for filters. To create a report - open the existing report, on the Report Tools - Design tab - select "Manage" to rename the report or Copy to create a copy of the report and edit.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Example Report Hinchy Word 0 10-09-2012 07:00 AM
Best way for tracking and report Osama.Mujahed Project 3 02-05-2012 06:39 AM
How to edit the "Format" and the "show level" of an EXISTING table of content? Jamal NUMAN Word 2 08-14-2011 10:46 AM
MarkAsFinal - 'Edit Anyway' edit popup issue GovindRS PowerPoint 1 06-20-2011 06:43 AM
Report creation. Igtech Excel 1 04-02-2010 03:33 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:26 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft