Multiple resources allocated when only one was selected
Hi, I'm having an issue with resource allocation in Project'07, when opening the Assign Resource screen the resources all start by being selected, clicking on one resource and then the Assign button causes all resources to become allocated. If I then click Undo the problem is instantly fixed and the correct resource is assigned, or if I press Enter instead of clicking the button it works as it should.
Does anyone have any ideas as this problem doesn't seen to occur on every computer? |
#2
|
|||
|
|||
If this only occurs with a few computers, I'd check the service pack level applied to Project 2007. The most current SP is SP-3 - it should be installed.
Julie |
#3
|
|||
|
|||
Hi Julie, I did wonder if it was SP related. Many thanks, I'll try updating them. Regards, David
|
#4
|
|||
|
|||
Good luck, David. Let us know how you get along.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
adding multiple resources | Katy I | Project | 3 | 07-05-2012 02:18 PM |
How to set task to be done by 4 resources each one after another? | lukusm | Project | 1 | 01-16-2012 07:21 AM |
Over allocated with only 1300 hours in a year?!!! | msproject2010 | Project | 1 | 08-01-2011 04:29 AM |
Total Resources | 602chrislys | Project | 1 | 10-04-2010 09:04 AM |
Shared resources | ediez | Project | 0 | 08-18-2010 12:04 PM |