#1
|
|||
|
|||
project 2010 resource usage
Hi
i am a bit confused due to fixed duration vs fixed work if i have a task that are estimated to 8 hrs, the resource usage show 100%. bu if i change this to 2 day. unit does not change resource usage to 50% what do i do wrong |
#2
|
|||
|
|||
If the task is fixed Work and you increase the duration to 2 days, the Peak field will show the correct assignment units.
Display the Task usage or resource usage view and add the peak field. See: http://blogs.msdn.com/b/project/arch...ject-2010.aspx for a detailed description. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
MS Project - Resource usage printout | scrinmemphis | Project | 1 | 02-22-2013 02:30 PM |
Making Gantt chart and resource usage views independently viewable in MSP 2007 | proj12 | Project | 1 | 02-28-2012 06:59 AM |
resource leveling in ms project | ketanco | Project | 1 | 12-24-2011 12:58 PM |
Resource Usage sheet - options | Andy Bain | Project | 1 | 11-05-2010 12:42 PM |
MS Project Resource Chart | fherbert | PowerPoint | 0 | 09-09-2010 12:20 PM |