This is not MS Project Specific question but a schedule question.



The critical path is usually the longest path of a schedule. In what cases this is not true?
Reply With Quote
  #2  
Old 03-11-2013, 08:38 AM
JulieS JulieS is offline Critical Path Length Windows 7 64bit Critical Path Length Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The critical path is the series of tasks with float equal to zero. It is not necessarily the longest path in the project. Microsoft Project uses the forward and backwards pass to calculate float (Project refers to it as slack.).

Things like task calendars or constraints will change the float calculation and will change critical path.
Reply With Quote
  #3  
Old 03-15-2013, 10:53 AM
ketanco ketanco is offline Critical Path Length Windows 7 64bit Critical Path Length Office 2007
Expert
Critical Path Length
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
It is not necessarily the longest path in the project.
Why? Can you give a simple example?

Last edited by ketanco; 03-15-2013 at 11:56 AM.
Reply With Quote
  #4  
Old 03-15-2013, 11:34 AM
JulieS JulieS is offline Critical Path Length Windows 7 64bit Critical Path Length Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Things like task calendars or constraints will change the float calculation and will change critical path.
Reply With Quote
  #5  
Old 03-15-2013, 11:56 AM
ketanco ketanco is offline Critical Path Length Windows 7 64bit Critical Path Length Office 2007
Expert
Critical Path Length
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

so if they change the critical path then we will have a new critical path. but how is a critical path different than a longest path?
Reply With Quote
  #6  
Old 03-15-2013, 01:12 PM
JulieS JulieS is offline Critical Path Length Windows 7 64bit Critical Path Length Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Constraints will alter critical path by adding slack. Try an experiment. Add three tasks linked F to S. On the last task add a Must Finish On constraint with a date 1 day after the current scheduled date.
You'll see only the task with the constraint is critical. Remove the constraint.
Critical path appears for all tasks.
Add a Finish no Earlier Than constraint on the second task with a date 3 days later than its schedule. The first task drops off critical path.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Critical Path Length analysing contractor schedule for critical path ketanco Project 1 02-07-2013 06:49 AM
tying to a critical activity ketanco Project 1 08-04-2012 05:59 AM
critical path starting in future ketanco Project 5 07-27-2012 02:50 PM
calculate multiple critical paths ketanco Project 3 12-26-2011 09:29 AM
Critical Path Length Critical Path w/ 2 Calendars AndreT Project 6 07-27-2011 11:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:41 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft