Hi


Wondered if anyone has any idea on how to programmatically create a link from one task start or end date to another, therein allowing me to create a hammock task,
To do this manually, you would select the start date, click copy, select start date if task to be hammocked, click paste special, Paste Link and OK.

Cheers
Reply With Quote
  #2  
Old 03-08-2013, 08:58 AM
JulieS JulieS is offline Use VBA to create Hammock Tasks Windows 7 64bit Use VBA to create Hammock Tasks Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Answered at:
http://social.msdn.microsoft.com/For...5-c9bbe346e02d
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
updating not completed tasks or 0% tasks ketanco Project 3 08-24-2012 05:59 AM
My Tasks--To Do List? markg2 Outlook 0 06-01-2012 08:21 AM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM
Scheduling of Tasks asmith1977 Project 0 01-27-2011 11:13 AM
Use VBA to create Hammock Tasks Why red tasks at last 3 tasks of 21 tasks Jochen Project 2 04-13-2009 07:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:03 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft