Dear all,



I have a question related with the way MS Project make the resource levelling. Here is a simple example to explain my question:

"3 workers are available to perform any of the two tasks related to the project. However, tasks cannot be done by more than 2 workers at the same time..."

(see image attached)

...Why both activities don't start at the same time, with 2 workers on one task and 1 worker in the other until the first task is finished?
Attached Images
File Type: jpg MS Levelling Question.jpg (114.4 KB, 11 views)
Reply With Quote
  #2  
Old 03-08-2013, 09:01 AM
JulieS JulieS is offline MS Project - Maximizing resource levelling Windows 7 64bit MS Project - Maximizing resource levelling Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hello aguatorito,
I'm afraid that is not how the resource leveling command works.
  • It will never assign resources.
  • It will never reallocate resources
All the resource leveling command will do is delay tasks until peak units is less than or equal to max units.


If you have 3 resources available, why not assign all 3?
Reply With Quote
  #3  
Old 03-09-2013, 07:43 AM
aguatorito aguatorito is offline MS Project - Maximizing resource levelling Windows XP MS Project - Maximizing resource levelling Office 2007
Novice
MS Project - Maximizing resource levelling
 
Join Date: Mar 2013
Posts: 2
aguatorito is on a distinguished road
Default

Hi Julie,

Thanks for your reply. I was afraid that MS Project doesn't allow this kind of levelling, but I still had some hope on it.

As I mentioned, this is just a small example of what I really have: over 20 activities that can be done by 2 to 6 workers (no less, no more), and a total of approx. 30 workers available that can perform any task.

Thanks anyway,
Aguatorito
Reply With Quote
  #4  
Old 03-10-2013, 06:08 AM
JulieS JulieS is offline MS Project - Maximizing resource levelling Windows 7 64bit MS Project - Maximizing resource levelling Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The best I can suggest is always assign the maximum number of workers who can perform the tasks. You can create the work resources as max units of 3000% to indicate you have 30 workers. However, project will still not assign additional workers to tasks.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
MS Project - Maximizing resource levelling MS Project - Resource usage printout scrinmemphis Project 1 02-22-2013 02:30 PM
MS Project - Maximizing resource levelling Create a resource sheet in MS Project chabuk1 Project 8 05-01-2012 12:59 PM
MS Project - Maximizing resource levelling resource leveling in ms project ketanco Project 1 12-24-2011 12:58 PM
MS Project - Maximizing resource levelling Resource Column in MS Project 2003 seenai Project 18 06-10-2011 03:23 AM
MS Project Resource Chart fherbert PowerPoint 0 09-09-2010 12:20 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:57 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft