ketanco ketanco is offline how to calculate backwards from a set finish date Windows 7 64bit how to calculate backwards from a set finish date Office 2007
Expert
how to calculate backwards from a set finish date
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default how to calculate backwards from a set finish date

Hello


They have told me to end a certain project at a fixed date and calculate everything before that according to that fixed date. I went into the last task and tried to do "finish no later than" but it didnt have any effect.

how can i calculate everything on a schedule based on a fixed end date that must not change? they want to see when they should start the project. i know that by iteration of the initial date to various dates i can also do this but i want to know if there is a better way
Reply With Quote
  #2  
Old 02-07-2013, 06:50 AM
JulieS JulieS is offline how to calculate backwards from a set finish date Windows 7 64bit how to calculate backwards from a set finish date Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

On a copy of the schedule, switch specify the Finish date in Project Information.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
how to calculate backwards from a set finish date Units not properly updated after a Finish Date Change zi1 Project 1 08-04-2012 05:55 AM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM
how to calculate backwards from a set finish date Calculate date in word field edwedw Mail Merge 3 11-30-2011 02:10 PM
how to calculate backwards from a set finish date Formula to auto calculate Day of the week based on Date prasad@dmci.ca Excel 1 11-29-2011 01:05 PM
how to calculate backwards from a set finish date Using Field Codes to Calculate 5 years from a Date vandy Word 1 09-23-2009 11:32 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:43 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft