Baseline query
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default Baseline query

Hi

I have had to add a few new tasks to my baselined schedule. Should I update the current baseline or create a new baseline?



What is the impact on the project statistics which I am reporting weekly when doing either of the above? Should I just expect to see the difference in the current and baselined work which should equate to the number of work hours added in the new tasks? Just trying to figure out what impact this will have on my reporting.

Thanks for your help

Jo
Reply With Quote
  #2  
Old 01-23-2013, 10:21 AM
joday48 joday48 is offline Baseline query Windows 7 64bit Baseline query Office 2010 32bit
Novice
Baseline query
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default Just to follow up

I actually re-set the baseline and extracted my stats. I can explain the difference in the baseline figures.

What I have lost is all the original work variance that I report on weekly. It now simply shows that everything was completed exactly in line with the tasks baselined work. Ie; it's saying a task had baseline of 1 hour, work of 1 hour and actual work of 1 hour.

I know the task actually had (before updating the baseline), baseline of 2 hours, work of 1 hour and actual work of 1 hour. Giving a variance of -1 hr.

I've lost all this data. How can I get it back, or what should I have done differently? I have a copy of the schedule saved prior to resetting this baseline so if someone could please let me know, there may be a chance I can start again with the saved, original version, and keep my variances!

Thanks for your help

Jo
Reply With Quote
  #3  
Old 01-23-2013, 11:38 AM
JulieS JulieS is offline Baseline query Windows 7 64bit Baseline query Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Before re-baslining copy your original baseline to Baseline1. That will preserve your original baseline. Then over write the baseline with a new one.

You can change which baseline is used to calculate variance in File > Options, Advanced, Earned value section. (Project 2010).
Reply With Quote
  #4  
Old 01-24-2013, 04:56 AM
joday48 joday48 is offline Baseline query Windows 7 64bit Baseline query Office 2010 32bit
Novice
Baseline query
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default

Hi Julie

Thanks for replying. I am unsure how to copy my original baseline to baseline 1. I can see there is a copy function on interim plan but not the baseline option.

Can you talk me through this please?

I don't want to lose all the variance data I have.

Thanks

Jo
Reply With Quote
  #5  
Old 01-24-2013, 10:48 AM
JulieS JulieS is offline Baseline query Windows 7 64bit Baseline query Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

in Project 2010:

Project tab > Set Baseline > Set baseline.
click Set Interim Plan
Copy Baseline
Intro: Baseline 1

You can then set the calculation of variance through File > Options, Advanced.
Reply With Quote
  #6  
Old 01-25-2013, 06:47 AM
joday48 joday48 is offline Baseline query Windows 7 64bit Baseline query Office 2010 32bit
Novice
Baseline query
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default

Thank you Julie, it was the interim part that threw me.
Reply With Quote
  #7  
Old 01-25-2013, 09:50 AM
JulieS JulieS is offline Baseline query Windows 7 64bit Baseline query Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome, Jo. Glad to have helped and thanks for the feedback.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to Query Text in MS-Excel 2010 or Import Data & Query outside of Excel? mag Excel 0 10-18-2012 11:15 AM
I didn't save a baseline joday48 Project 5 07-05-2012 02:19 PM
some work was complete at my baseline ketanco Project 1 01-25-2012 02:45 PM
Baseline query Retrieve a baseline after it's been cleared fridos Project 2 05-11-2011 10:08 AM
Baseline query Help with Interim Baseline Variance poyns Project 1 05-27-2010 10:59 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:39 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft