Assigning Resources to Tasks
Having a very difficult time figuring this out.
Scenario - Project 2010 Create a task that has a DURATION of 20 days and WORK of 40 hours. This means I expect 10 hours of work to be done per week. I assign two resources. One at 25% and one at 75%. When I view the Resource Usage sheet I expect to see 2.5 hours per week for resource 1 and 7.5 hours per week for resource 2. THe Resource Sheet does not show this at all. It seems to screw it up all the time. Am I even setting this up right? There will be several tasks that will have work hours set over a longer duration with multiple resources at various percentages so I have to get this right. Thanks! Rick |
#2
|
|||
|
|||
answered on Microsoft Answer forums:
http://answers.microsoft.com/en-us/o...7-977792a9c45d |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
updating not completed tasks or 0% tasks | ketanco | Project | 3 | 08-24-2012 05:59 AM |
Changing resources against tasks with actual values | joday48 | Project | 3 | 06-28-2012 05:13 AM |
Assigning calendars to resources automatically | david_23 | Project | 3 | 03-30-2012 07:43 AM |
Export Excel tasks into Outlook Tasks (2007 Version on both) | crazedmom | Excel | 0 | 12-29-2011 07:55 AM |
Assigning resources. | Sergey M | Project | 0 | 01-25-2006 09:33 AM |