Bar in the Gantt chart with the duration
Hello everyone,
This is a simple question. Here is I want to do. I want to have a task that has 2 month duration. Let's say it starts from January 1st 2013. I assume that the bar in the gantt chart will end in the end of February 2013. But, it ends on February 25th 2013. I notice that it is because it uses 20 working day calendar. It is possible to change the working days of the calender, but I think there is better solution. How can I go around this issue (to have this bar extended until the end of february 2013) ? Any advice will be appreciated. |
#2
|
|||
|
|||
It depends upon what you are trying to accomplish - if you don't intend to assign resources, you could use elapsed duration - for example 2emo in the duration field will give you 60 calendar days including non-working days.
The trouble is if you assign resources, they will be assigned for 24 hours per day for the elapsed day duration - so your work values will be wildly inflated. Julie |
#3
|
|||
|
|||
Thanks for your helpful response Julie,
|
#4
|
|||
|
|||
You're welcome. Feel free to post back if you have questions or need further clarification.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Gantt Chart with split view | Intruder | Project | 5 | 12-20-2012 08:35 AM |
move to first date on gantt chart | etsoft | Project | 3 | 12-23-2011 08:32 AM |
Links to several milestones on same line of a Gantt chart | viv_2_k | Project | 3 | 08-03-2011 04:40 AM |
Exporting Gantt Chart to MS Word 2007 | earweed | Project | 4 | 06-02-2011 09:21 AM |
Gantt Chart: MS Project vs. Excel | Nance | Project | 2 | 12-09-2008 01:59 PM |