Summarize durations by top level task
Can anyone help me summarise the durations each task by top level task for each participant? |
#2
|
|||
|
|||
Are you looking for total work per resource? Assignments (resources + tasks) do not have duration but work.
Try this: Apply the Task Usage view Ensure the Work field is in the table on the left. Create a new group Group first by Outline Number Then by Resource Names Check the box "group assignments not tasks" and set the group by on Resource Names to assignments. This will show you summary level 1 tasks and the resources assigned to the tasks underneath. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Changing TOC from 2-level to 3-level | SQLUSA | Word | 6 | 07-23-2012 06:21 AM |
Milestone durations | fraserm | Project | 4 | 01-13-2012 08:43 AM |
Adjusting All Durations by 10% | skoz55 | Project | 1 | 01-13-2012 08:26 AM |
Task and Summary Durations | JR_12 | Project | 0 | 10-15-2011 05:07 PM |
Custom field formula not working at summary task level | abw1987 | Project | 3 | 10-05-2011 07:17 AM |