ms_user ms_user is offline Bar in the Gantt chart with the duration Windows XP Bar in the Gantt chart with the duration Office 2010 32bit
Novice
Bar in the Gantt chart with the duration
 
Join Date: Jan 2013
Posts: 6
ms_user is on a distinguished road
Default Bar in the Gantt chart with the duration

Hello everyone,
This is a simple question.
Here is I want to do.
I want to have a task that has 2 month duration.
Let's say it starts from January 1st 2013.
I assume that the bar in the gantt chart will end in the end of February 2013. But, it ends on February 25th 2013.
I notice that it is because it uses 20 working day calendar.


It is possible to change the working days of the calender, but I think there is better solution.
How can I go around this issue (to have this bar extended until the end of february 2013) ?
Any advice will be appreciated.
Reply With Quote
  #2  
Old 01-10-2013, 11:15 AM
JulieS JulieS is offline Bar in the Gantt chart with the duration Windows 7 64bit Bar in the Gantt chart with the duration Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

It depends upon what you are trying to accomplish - if you don't intend to assign resources, you could use elapsed duration - for example 2emo in the duration field will give you 60 calendar days including non-working days.

The trouble is if you assign resources, they will be assigned for 24 hours per day for the elapsed day duration - so your work values will be wildly inflated.

Julie
Reply With Quote
  #3  
Old 01-10-2013, 07:43 PM
ms_user ms_user is offline Bar in the Gantt chart with the duration Windows XP Bar in the Gantt chart with the duration Office 2010 32bit
Novice
Bar in the Gantt chart with the duration
 
Join Date: Jan 2013
Posts: 6
ms_user is on a distinguished road
Default

Thanks for your helpful response Julie,
Reply With Quote
  #4  
Old 01-11-2013, 06:31 AM
JulieS JulieS is offline Bar in the Gantt chart with the duration Windows 7 64bit Bar in the Gantt chart with the duration Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome. Feel free to post back if you have questions or need further clarification.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Bar in the Gantt chart with the duration Gantt Chart with split view Intruder Project 5 12-20-2012 08:35 AM
move to first date on gantt chart etsoft Project 3 12-23-2011 08:32 AM
Bar in the Gantt chart with the duration Links to several milestones on same line of a Gantt chart viv_2_k Project 3 08-03-2011 04:40 AM
Exporting Gantt Chart to MS Word 2007 earweed Project 4 06-02-2011 09:21 AM
Bar in the Gantt chart with the duration Gantt Chart: MS Project vs. Excel Nance Project 2 12-09-2008 01:59 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:32 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft