Evgeny Evgeny is offline Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Windows 7 64bit Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Office 2007
Novice
Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all
 
Join Date: Dec 2012
Posts: 3
Evgeny is on a distinguished road
Default Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all

Dear all,

If I look at it, Microsoft Project effectively has 5 types of tasks (fixed duration, fixed units, fixed work. Plus each of them can be either effort driven or not effort driven, except fixed work, which is always efforts driven)

I am using MS Project quite for a while, but I could never really understand, why Microsoft effectively has 5 types of tasks, why it is needed, and in which situation use one and not the other. For my schedules I use most of the time fixed duration and sometimes fixed work.

Does anyone has a good guideline about this?

Regards.

Evgeny
Reply With Quote
  #2  
Old 12-24-2012, 02:08 PM
JulieS JulieS is offline Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Windows 7 64bit Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi,

There are only 3 true task types - fixed duration, fixed work, fixed units. The task type determines which of the 3 variables change when you change one of the other.

Fixed Duration
You change work - Project changes Units
You change Units - Project changes work

Fixed Work
You change duration - Project changes units
You change units - Project changes work

Fixed Units
You change duration - Project changes work
You change work - Project changes duration.

Effort driven and non-effort driven determine what occurs if you add or subtract named resources. If the task is effort driven and you add or subtract named resources, the total amount of work on the task remains the same. In effort driven fixed units and effort driven fixed work - add more resources and duration decreases. In effort driven fixed duration - add more resource and units decreases.

Non-effort driven tasks - if you add more resources, work increases. Remove resources, work decreases.

I hope this helps.
Julie
Reply With Quote
  #3  
Old 01-03-2013, 04:29 AM
Evgeny Evgeny is offline Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Windows 7 64bit Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Office 2007
Novice
Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all
 
Join Date: Dec 2012
Posts: 3
Evgeny is on a distinguished road
Default

Julie,

thank you for your answer. I tested it, and it is more or less clear.

I can see also, that there are also differences in other places: e.g. what happens if resource and a task has different calendars, etc. I will do some more testing and may be publish results here.
Regards.
Evgeny
Reply With Quote
  #4  
Old 01-03-2013, 06:45 AM
JulieS JulieS is offline Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Windows 7 64bit Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome.

Calendars are also mostly clear. When a task is first created its schedule is driven by the definition of working and non-working in the project calendar. (Set in Project Information).

Resource also have their own calendars that are created when the resource is created.

When a resource is assigned to a task, the definition of working and non-working time in the resource's calendar becomes the schedule driver.

You may also assign specific calendars to tasks on the Advanced tab of the Task Information dialog. When assigning a calendar to a task you can select whether the resource's calendar is ignored - otherwise the task will be scheduled for common working time between the task calendar and the resource's calendar.

I hope this helps.
Julie
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to add a fixed value to an entire column? mikehende Excel 11 12-12-2012 02:47 PM
Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
Task duration between 2 fixed milestones cettolox Project 3 01-24-2012 06:33 AM
Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Quick Click not fixed in SP3? implus it Outlook 2 11-09-2011 01:30 PM
Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Time now--fixed? markg2 Excel 1 09-19-2010 12:05 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:54 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft