Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 11-29-2012, 04:16 PM
seanpears99 seanpears99 is offline Amending dates and recalculating duration Windows 7 64bit Amending dates and recalculating duration Office 2007
Novice
Amending dates and recalculating duration
 
Join Date: Oct 2011
Posts: 12
seanpears99 is on a distinguished road
Default Amending dates and recalculating duration

Hi

I am using 2010 professional in a server environment, in the top half of our schedule template we have some stage durations which have cost resources assisgned and the dates and costs from these tasks are pulled into a status report through BI.


The top half is basically a report and the users need to adjust stage start and end dates on a regular basis.
My question is, does the duration always take priority when amending dates, i.e. if you shift out an end date manually, the duration is honoured and pulls the start date out too. Can I change this so that the start date doesnt move.
Basically these dates are constraints purely for the benefit of the status report, I can use manually scheduled tasks but then you cannot adjust the budgets for the tasks so they have to be auto.
I need the use to amend a start date or end date and reflect the new duration, not honour it and pull either the end or start with it?
I know this wont make scheduling sense, its purely for reporting.
Thanks
SP
Reply With Quote
  #2  
Old 12-03-2012, 07:18 AM
JulieS JulieS is offline Amending dates and recalculating duration Windows 7 64bit Amending dates and recalculating duration Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi seanpears99,

No, sorry. No combination of task type is going to allow you to chance dates manually and increase duration. When you manually enter a finish date, Project sets a FNET (finish no earlier than) constraint, maintains the duration, and moves the start date.

The only work around would be to set the task at a low level (1%) complete which sets an Actual Start date. If you then change finish date, the start date will not move.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
start and finish dates exceeding duration joday48 Project 0 06-27-2012 04:55 AM
Amending dates and recalculating duration baseline duration, start and finsih dates ketanco Project 1 04-09-2012 09:47 AM
Amending templates on a Mac graham Word 0 01-05-2012 10:12 AM
Amending dates and recalculating duration duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
Amending dates and recalculating duration Duration does not change caz46 Project 1 05-17-2011 07:51 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:14 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft