|
#1
|
|||
|
|||
Hi seanpears99,
No, sorry. No combination of task type is going to allow you to chance dates manually and increase duration. When you manually enter a finish date, Project sets a FNET (finish no earlier than) constraint, maintains the duration, and moves the start date. The only work around would be to set the task at a low level (1%) complete which sets an Actual Start date. If you then change finish date, the start date will not move. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
start and finish dates exceeding duration | joday48 | Project | 0 | 06-27-2012 04:55 AM |
baseline duration, start and finsih dates | ketanco | Project | 1 | 04-09-2012 09:47 AM |
Amending templates on a Mac | graham | Word | 0 | 01-05-2012 10:12 AM |
duration vs actual start and finish dates | ketanco | Project | 1 | 12-14-2011 09:06 AM |
Duration does not change | caz46 | Project | 1 | 05-17-2011 07:51 AM |