#1
|
|||
|
|||
Missing Tasks from Network Diagram View
Hi Folks
I have a project plan with all Predecessors and Successors correctly filled in (I hope ). However when I choose to view the Network Diagram a number of sub tasks do not show up. I have the same problem with Project 2007 and Project 2010. Any advice/help would be appreciated. Tony |
#2
|
|||
|
|||
I'm guessing you discovered that if the subtasks are not visible (collapsed) in the Gantt chart view, they are collapsed in the Network diagram?
|
#3
|
|||
|
|||
Hi Julie
No. It was because the tasks had dependencies which pushed the tasks way out to the right hand side of the Network Diagram and I missed them lol. Thanks Tony |
#4
|
|||
|
|||
Great - I'm glad you found them! Thanks for the solution to the mystery.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Excel 2010 view of cel missing | isla | Excel | 2 | 09-27-2013 09:35 AM |
network diagram arrows | ketanco | Project | 3 | 02-14-2013 10:46 AM |
Date showing 01/01/84 in Network Diagram - Project 2010 | JHBPJF | Project | 1 | 05-04-2012 07:52 AM |
arrows not showing in certain sections of network diagram | ketanco | Project | 1 | 12-24-2011 12:50 PM |
network diagram colors and corsses meanings | ketanco | Project | 1 | 12-14-2011 02:41 PM |