#1
|
|||
|
|||
Task Information Dialog Box
This is a suggestion.
In the Task Information Dialog box, when predecessor data is shown it would be very helpful if % Complete would be displayed. As a PM, if I'm looking at upcoming tasks to determine whether they will start on time, one of the data points I need is the status of previous activities. Having easy access to the % Complete would make that job much simpler and quicker. |
#2
|
|||
|
|||
Hi,
As a quick check, display the task form in the lower pane formatted to show predecessors and successors. You can then double click on the predecessor task in the task form, to show the Task Information form, with % complete, for the task. I hope this helps. Julie |
#3
|
|||
|
|||
Julie,
Thank you for the reply. I was aware of that option and do use it. Unfortunately many of my projects are very complex and a single task may have very many predecessors. Having to select and view each one individually can get time consuming. Having the % Complete available would give a very handy snapshot and allow the PM to concentrate on those tasks that are threats to starting on time. |
#4
|
|||
|
|||
I understand - but truthfully, you will not catch the eye of Microsoft here.
Try: http://office.microsoft.com/en-us/suggestions.aspx |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
seeing successor information for a task | ketanco | Project | 1 | 06-02-2012 09:35 AM |
arrows remain between task bars, but predecessor info disappears from task info | Antares | Project | 1 | 12-14-2011 09:19 AM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
Suppress Dialog Box | crutch024 | Word | 0 | 08-17-2010 09:52 AM |
Password dialog | akwoods | Outlook | 2 | 01-09-2006 09:09 AM |