#1
|
|||
|
|||
Total Time in 2003
Hi,
The duration column reflects the elapsed time of tasks but I want to look at the man days required to achieve the task (or tasks). For example I have a plan where the elapsed time for a bunch of tasks is 25 days but the total man days to do the tasks is 94 days. I want to be able to see a column which displays the 94 days. Can anybody advise which column looks at this. Many thanks for any help. Cheers John |
#2
|
|||
|
|||
If you've assigned resources, the Work field shows work or effort and should roll up all work from subtasks into a summary task.
Duration = span of time (in working time) from the task start to task finish. It is not elapsed time as elapsed time counts non-working time (weekends, holidays etc.) I hope this helps. Julie |
#3
|
|||
|
|||
Thanks
Hi Julie,
Many thanks. I'd figured it out. Regards John |
#4
|
|||
|
|||
You're welcome, John and thanks for the feedback.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
display in meeting 'When' show old time on 2007-10 but not in 2003 | andrelabbe | Outlook | 0 | 07-18-2012 03:01 AM |
IE Object: Run-time problem (the link is not clicked in run-time but not in step-in | tinfanide | Excel Programming | 1 | 03-04-2012 12:05 AM |
Error Outlook 2003 " Receive much mail the same at the same time" | nhat2nhat2 | Outlook | 1 | 09-26-2011 11:10 PM |
Total Resources | 602chrislys | Project | 1 | 10-04-2010 09:04 AM |
Issues with Total # of Pages | zehra216 | Word | 2 | 07-06-2009 08:41 AM |