Actual working hours per day
 
Join Date: Jan 2008
Posts: 1
climbatron
Default Actual working hours per day

I have a team of resources who complete projects, but their daily is interrupted by other tasks, phone calls, meetings etc.



Their standard daily hours are 7.5 hours, but I want to restrict their working time on a project to 6.5 hours to take into account interruptions.

I have currently done this by changing the working time, but, this affects the cost calculations, as they should be paid for all 7.5 even though only 6.5 are allocated to a project.

Is there a better way to do this? Should I be using the resoure available units?

Thanks

Paul
Reply With Quote
  #2  
Old 12-16-2015, 09:37 AM
Margaret Pate Margaret Pate is offline Actual working hours per day Windows 10 Actual working hours per day Office 2013
Novice
 
Join Date: Dec 2015
Posts: 12
Margaret Pate is on a distinguished road
Default

Have you changed the hours per day to 6.5 in the Options, schedule? If you try this remember to change the hours per week as well.
Reply With Quote
  #3  
Old 12-17-2015, 03:13 PM
JulieS JulieS is offline Actual working hours per day Windows 7 64bit Actual working hours per day Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Paul,
I'm sorry there is no method to have the cost calculated based upon 7.5 hours per day but have the duration based upon 6.5 hours per day. Cost is always based upon work - so changing assignment units will change the duration - but the work will remain the same. The best I can suggest is to adjust the cost so the rate of 7.5 per day is applied to a 6.5 hour day.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
working with html kate1234 Word 0 09-22-2008 05:02 PM
Merge mail not working jdpowell@brazoriainet.com Mail Merge 1 07-25-2008 07:51 PM
Spell Check Not Working Butch Jackman Word 0 10-18-2006 11:18 AM
Actual working hours per day Excell stopped working TomC Excel 4 05-26-2006 11:40 PM
New install outlook not working lost Outlook 0 12-16-2005 05:32 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:12 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft