ketanco ketanco is offline activities getting constraint dates vs starting as soon as possible Windows 7 64bit activities getting constraint dates vs starting as soon as possible Office 2007
Expert
activities getting constraint dates vs starting as soon as possible
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default activities getting constraint dates vs starting as soon as possible

Hello,
As a result of updating my schedule on some activities it automatically inserted a start no earlier than constraint, for example when i told the project to schedule unstarted activties after current data date.



Is having these constraints bad for my schedule logic? especially after i do other updates later on that version?

Also is there a way to remove all these alltogether at once or we can only remove these constraints one by one. (to make it start as soon as possible)

by making them start as soon as possible actually is more healthy as far as the schdule loogic as long as i do the correct schedule logic instead of not correcting the wrong logic and inserting actual dates am i right?
Reply With Quote
  #2  
Old 08-30-2012, 05:27 AM
JulieS JulieS is offline activities getting constraint dates vs starting as soon as possible Windows 7 64bit activities getting constraint dates vs starting as soon as possible Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

As a result of updating my schedule on some activities it automatically inserted a start no earlier than constraint, for example when i told the project to schedule unstarted activties after current data date.

This is expected as part of the reschedule. If the tasks retained the ASAP constraint, they would be scheduled in the past.

Is having these constraints bad for my schedule logic? especially after i do other updates later on that version?

No. If the tasks have constraints from the reschedule command that is, in my opinion, better than remaining work in the past. If you run another update and the task still has remaining work, that will be rescheduled again to the future.

Also is there a way to remove all these alltogether at once or we can only remove these constraints one by one. (to make it start as soon as possible) by making them start as soon as possible actually is more healthy as far as the schdule loogic as long as i do the correct schedule logic instead of not correcting the wrong logic and inserting actual dates am i right?

Select all tasks, show the task information dialog box. Go to the Advanced tab and change the constraint. However, that will force remaining work in the past.

Again - there is a difference between constraints forced by progressing the project and using constraints (usually through typing dates) in the initial planning. You should have both correct scheduling logic driven by task predecessor and successor relationships initially. Actuals (actual start, actual finish, actual work, etc) over-ride that scheduling logic and constraints added by rescheduling is more logical than incomplete tasks in the past.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
activities getting constraint dates vs starting as soon as possible Update Progress breaks with constraint benwimpory Project 1 03-14-2012 08:44 AM
splitted bars of activities ketanco Project 6 02-11-2012 07:17 AM
activities getting constraint dates vs starting as soon as possible Adding or removing activities after basline ketanco Project 3 01-25-2012 06:43 AM
Link activities and milestones between projects (2003) jowian Project 0 11-25-2010 09:10 AM
OL 2010 Public Contact Activities ibstech Outlook 0 08-05-2010 10:25 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:39 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft