#1
|
|||
|
|||
% complete problem
Ok, very simply:
As an example; I have two tasks, both are 10 days but one is 100% complete and one is 0% complete. The first task took 10 men 10 days to complete, however the second task takes 1 man 10 days to complete. I should therefore have % complete greater than 50% but it doesn't - it says I am only 50% complete because it sees the duration is 20 days and ten days are finished = 50%. But the work to do the first task takes more effort than the second and in reality I should be 90% complete. So what is the problem, what is wrong? It's driving me nuts. |
#2
|
|||
|
|||
Try % Work complete added to the summary task line.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
complete % and physical complete % | ketanco | Project | 3 | 05-25-2012 08:19 AM |
some work was complete at my baseline | ketanco | Project | 1 | 01-25-2012 02:45 PM |
% Complete (Actual) vs % Complete (Should) | Carlos Maximo | Project | 3 | 12-06-2011 12:01 PM |
Problem to complete creation of new e-mail account | Momentum | Outlook | 0 | 03-31-2011 02:31 PM |
Complete beginner needs some help. | Biofodder | Word VBA | 1 | 03-14-2011 01:49 AM |