JulieS JulieS is offline Units not properly updated after a Finish Date Change Windows 7 64bit Units not properly updated after a Finish Date Change Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I've answered you on the Tek Tips forum:

http://tek-tips.com/threadminder.cfm?pid=913&page=1
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Units not properly updated after a Finish Date Change How do I get auto-updated "number of days since specified date" on MS word? terry795 Word 16 01-07-2016 04:33 PM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM
Automatic Date Change Marusja Word 0 03-04-2009 03:45 AM
Units not properly updated after a Finish Date Change Imported message date change to today's date promark Outlook 1 12-23-2005 07:21 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:42 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft