Old 07-21-2012, 03:46 PM
lylel lylel is offline Change Resource Time vs. Duration when Updating Work column Windows XP Change Resource Time vs. Duration when Updating Work column Office 2010 32bit
Novice
Change Resource Time vs. Duration when Updating Work column
 
Join Date: Jul 2012
Posts: 2
lylel is on a distinguished road
Default Change Resource Time vs. Duration when Updating Work column


Whenever I change the amount of time in the Work column because a task is either going to take more or less time that originally anticipated, Project defaults to changing the Duration column. 99% of the time I want the duration to stay the same and the amount of time that the resource is working on the task to change instead, so I have to go in and select the "Increase the hours resources work per day, so the task duration stays the same." or "Decrease the hours resources work per day, so the task duration stays the same." option, depending on whether I raised or lowered the amount of work time. Is there a way to make that option the default, so I don't have to take that extra step every time?
Reply With Quote
  #2  
Old 07-23-2012, 06:05 AM
JulieS JulieS is offline Change Resource Time vs. Duration when Updating Work column Windows 7 64bit Change Resource Time vs. Duration when Updating Work column Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Set you task types as fixed duration and then as you change work, duration will remain stable and the peak units will change.

You may add the "Type" field to the task view to change many tasks easily OR select all tasks (except summary), click the Information button on the Task tab, and set the task type on the Advanced tab.

I hope this helps.

Julie
Reply With Quote
  #3  
Old 07-23-2012, 02:22 PM
lylel lylel is offline Change Resource Time vs. Duration when Updating Work column Windows XP Change Resource Time vs. Duration when Updating Work column Office 2010 32bit
Novice
Change Resource Time vs. Duration when Updating Work column
 
Join Date: Jul 2012
Posts: 2
lylel is on a distinguished road
Default

Thank you for the information, I tried this and it solved the part about the duration changing, but now the Resource percentage won't change, but I need it to change. So, for example, if I have a task for "Mike" set for 1 hour, the Resource Name column says Mike[13%]. If I change the task to 2 hours, I want that column to say Mike[25%], but it stays at 13%. Is there any way to fix this part too?
Reply With Quote
  #4  
Old 07-23-2012, 06:09 PM
JulieS JulieS is offline Change Resource Time vs. Duration when Updating Work column Windows 7 64bit Change Resource Time vs. Duration when Updating Work column Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

There is a long series of discussion surrounding Assignment Units vs Peak units regarding Project 2010. See:

http://blogs.msdn.com/b/project/arch...ject-2010.aspx

for a beginning. The issue is you are seeing assignment units when it is Peak Units that show the correct value. Peak Units are only meaningful in the Task Usage or Resource Usage view.

So, the short answer is no. However you can add the Peak Units and Assignment Units field to the Task Usage view and copy the Peak units over the assignment units field to see what you need.

My recommendation is to NOT show assignment units with the bars in the Gantt chart. It just gets too deep into the mire to try to explain to others who may look at your Gantt chart and not fully understand how work, duration and units are related.
Reply With Quote
Reply

Tags
duration, resource, work



Similar Threads
Thread Thread Starter Forum Replies Last Post
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM
Can I change the horizontal scrollbar to scroll smoothly rather than column by column carpat Excel 0 01-10-2012 09:34 AM
Change Resource Time vs. Duration when Updating Work column baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM
Work not changing duration benoldays Project 0 02-14-2011 08:21 PM
Duration changes fail to update work effort Panteledes Project 6 05-25-2010 02:27 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:28 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft