Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 07-05-2012, 12:53 AM
joday48 joday48 is offline Actual work in the future Windows 7 64bit Actual work in the future Office 2010 32bit
Novice
Actual work in the future
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default Actual work in the future

Morning all



I've realised after updating my project and re-scheduling uncompleted work that project has scheduled actual work into the future.

I believe the problem has arisen because I have been using the % work complete field to update progress, and that Project does not take the current or the status date into account when you are using any of the % complete fields for entering actuals. I believe (please confirm) that in order for Project to move any actual work to the left of the Status date that you need to enter progress by entering Actual Work values.

Can someone please give me some guidance on:

1) Exactly how I should enter actual values in order for Project to take into consideration the status date and therefore leave any actual work to the left of the status date

2) Tell me how I can (quickly) change all the actual's I have already entered into my schedule so that all the progress currently entered is to the left of the status date.

I understand my method of entering actual values was not correct for project to do what I need it to do. I just need some guidance on the above points so that the schedule I am meant to present is not showing split tasks with actual values in the future.

If anyone would also like to elaborate on anything that I have said above please do so, I want as much understanding on the subject as possible.

Thanks in advance

Jo
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
can not delte actual dates in future ketanco Project 3 04-10-2012 05:34 AM
Actual work in the future entering future dates for a project that has started ketanco Project 5 12-15-2011 07:16 PM
Automatic scheduling of future events on creation of a new one TCS Outlook 0 02-17-2011 05:51 PM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM
Stop Future Recurring Meetings mileskb Outlook 0 06-03-2009 04:59 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:18 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft