Hi,
Is there a way to filter out tasks that are linked to one specific task (task A, ID 1) indirectly? I know how to filter out all tasks with lets say task A as predecessor. But if task C has task B as predecessor which in turn has task A as predecessor I will not found task C when I filter out tasks which has A as predecessor even though task C has task A as predecessor indirctly. Or should I avoid indirect dependencies and link all tasks to root task? |
#2
|
|||
|
|||
I don't believe there are any filters that will accomplish this. However, if you are using project 2010 you can "walk back" from predecessor to predecessor using the Task Inspector.
I think you need to set predecessors as dictated by the tasks in your project. If it is in a series, link it in a series. I hope this helps. Julie |
Tags |
dependencies, filter, indirect |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Help Date filter | Herve86 | Outlook | 0 | 05-28-2012 04:43 AM |
Data validation using indirect function | BullMouse | Excel | 2 | 11-30-2011 05:25 PM |
filter | kwlickt | Excel | 1 | 03-28-2011 11:15 AM |
Indirect | zleyphox | Excel | 1 | 02-11-2010 09:57 AM |
could you help me help me with advanced filter | Nora | Excel | 1 | 05-15-2009 11:10 AM |