Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 06-27-2012, 05:59 AM
joday48 joday48 is offline Changing resources against tasks with actual values Windows 7 64bit Changing resources against tasks with actual values Office 2010 32bit
Novice
Changing resources against tasks with actual values
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default Changing resources against tasks with actual values

Hi all



I have progress entered against some tasks assigned to a specific resource (person).

I have been told that the resource needs to change to a different person.

How can I do this without deleting the current resource (and in doing so the actual % work complete)? - I've had a look at deleting resource, but found that I had to literally enter all the task information (hours etc) again, and doing this didn't necessarily mean when I re-assigned with the new resource that the durations etc were being calculated correctly. There has to be a better way that I'm missing?

Can I not assign the second resource so that they pick up the remaining work and somehow set the original resource to have no remaining work? This way, all the dates and durations would do exactly what they should, and the resource profiles would show the original resource no longer working on that task.

Help!

Thanks all

Jo
Reply With Quote
  #2  
Old 06-27-2012, 09:21 AM
JulieS JulieS is offline Changing resources against tasks with actual values Windows 7 64bit Changing resources against tasks with actual values Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Jo,

Select the task, click the Resources ribbon and choose "Assign Resources" select the resource who is currently assign click "Replace" and select the replacement resource. The remaining work will be moved to the new resource and the actuals will remain assigned to the resource who performed the work.
Reply With Quote
  #3  
Old 06-28-2012, 01:03 AM
joday48 joday48 is offline Changing resources against tasks with actual values Windows 7 64bit Changing resources against tasks with actual values Office 2010 32bit
Novice
Changing resources against tasks with actual values
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default

Julie

Thanks ever so much. This explains why the original resource remained when I tried this before! I was not understanding what the replace actually did!

Thanks again

Jo
Reply With Quote
  #4  
Old 06-28-2012, 05:13 AM
JulieS JulieS is offline Changing resources against tasks with actual values Windows 7 64bit Changing resources against tasks with actual values Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome Jo, and thank you for the feedback.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Changing resources against tasks with actual values total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM
HELP! Powerpoint is changing my RGB values! christine PowerPoint 0 07-04-2011 09:25 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM
changing font size without changing leading carolns Word 1 09-14-2009 12:30 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:59 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft