#1
|
|||
|
|||
Changing resources against tasks with actual values
Hi all
I have progress entered against some tasks assigned to a specific resource (person). I have been told that the resource needs to change to a different person. How can I do this without deleting the current resource (and in doing so the actual % work complete)? - I've had a look at deleting resource, but found that I had to literally enter all the task information (hours etc) again, and doing this didn't necessarily mean when I re-assigned with the new resource that the durations etc were being calculated correctly. There has to be a better way that I'm missing? Can I not assign the second resource so that they pick up the remaining work and somehow set the original resource to have no remaining work? This way, all the dates and durations would do exactly what they should, and the resource profiles would show the original resource no longer working on that task. Help! Thanks all Jo |
#2
|
|||
|
|||
Hi Jo,
Select the task, click the Resources ribbon and choose "Assign Resources" select the resource who is currently assign click "Replace" and select the replacement resource. The remaining work will be moved to the new resource and the actuals will remain assigned to the resource who performed the work. |
#3
|
|||
|
|||
Julie
Thanks ever so much. This explains why the original resource remained when I tried this before! I was not understanding what the replace actually did! Thanks again Jo |
#4
|
|||
|
|||
You're welcome Jo, and thank you for the feedback.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
total slack not changing when changing duration | ketanco | Project | 1 | 02-11-2012 07:23 AM |
Export Excel tasks into Outlook Tasks (2007 Version on both) | crazedmom | Excel | 0 | 12-29-2011 07:55 AM |
HELP! Powerpoint is changing my RGB values! | christine | PowerPoint | 0 | 07-04-2011 09:25 AM |
MS Project able to import actual start and or actual finish date from Excel? | mhacker | Project | 0 | 04-26-2010 11:29 AM |
changing font size without changing leading | carolns | Word | 1 | 09-14-2009 12:30 PM |